Sunday |
Monday |
Tuesday |
Wednesday |
Thursday |
Friday |
Saturday |
| 1 | 2
Confirmed location of gas line. |
|||||
| 3
Cleaned moldy purlins with bleach and power sprayer. Purlins are permanently stained. Took pictures. |
4
Dug trench for power cable. Installed
string and conduit. Ordered floor trusses. Health dept. site visit to
discuss septic. |
5
Connected meter base, breaker box, and wiring to pole for temp power. Sent purlin pictures to Barna, who agreed to replace them. |
6
Septic installer site visit to discuss septic options. |
7
Installed plumbing in basement floor. |
8 | 9
Set temporary power pole and grounding
rod in trench. |
| 10 | 11
Delivered floor trusses. |
12
Set floor trusses. Delivered rest of
sub-floor materials. |
13
Completed half of sub-floor. Power company
connected temporary power. |
14
Completed sub-floor. BEGAN SETTING LOGS. |
15
Continued setting logs. |
16
Obtained window and door estimate. |
| 17 | 18
Continued setting logs. |
19
Continued setting logs. Obtained another
window and door estimate. |
20
Continued setting logs. |
21
Continued setting logs. |
22
Continued setting logs. |
23 |
| 24 | 25
Finished setting logs to top of first floor. |
26
Started setting beams for second floor. |
27
Started framing first floor wall
partitions. |
28
Set logs for gable end over bedrooms,
some above garage. Placed window and door order. |
29
Continued setting gable logs over garage
and foyer. Started constructing wall for shed dormer. |
30 |
| 31 | ||||||