Sunday |
Monday |
Tuesday |
Wednesday |
Thursday |
Friday |
Saturday |
| 1
Continued getting palettes from area businesses for log unloading site. |
2 | 3 | 4
Done additional dozer work to remove more
trees and level site for log delivery. |
5
Purchased and spread hay on unloading area.
|
||
| 6 | 7
DELIVERED LOG PACKAGE. |
8
Severe wind and thunderstorm last night.
Had to remove some debris from log package. |
9
Done additional dozer work to remove some close trees and do more site preparation. |
10
Dug basement and cut driveway. |
11 | 12
Bought items for temporary water
connection. Rented trencher and dug 250 ft. ditch for water line. |
| 13
Installed temporary drainpipe in driveway. |
14
Dug footers. Delivered Typar and 3 inch
gravel for driveway. |
15
Poured footers. Completed temporary water
connection. |
16
Delivered blocks for foundation. |
17
BEGAN LAYING BLOCK. (PHOTOS) Delivered portable
toilet. |
18
(Rained out.) Talked to Barna representative about missing materials for gabled porch, porch rafters and beams. |
19
Dug holes for perc test for septic system. Very bad perc. Need to call health dept. to discuss options. |
| 20
Started covering water line. |
21
Continued laying block. First termite
treatment done. |
22
Continued laying block. |
23
(Rained out.) Picked up meter base and items for temporary power. |
24
Continued laying block. Prepared more hay
and palettes for missing materials. |
25
Continued laying block. Delivered missing
materials. |
26
Purchased remaining materials for temporary power. Attempted to dig 250 ft. ditch for underground power cable; too rocky. |
| 27 | 28
(Rained out.) |
29
Continued laying block. Took pictures of
moldy purlins received in missing materials. |
30
FINISHED FOUNDATION. Measured foundation
for floor trusses. Sent purlin photos to Barna. |
31
Discussed floor truss options with Truss America and HVAC installer. Barna asked that we attempt to bleach purlins. |
||